The project
Mintz Levin needed a renovation and wanted to return unused space to the landlord, which meant a complex, 12-phase, 156,000 SF occupied restack. With 591 employees in Boston and no swing space, the work happened on evenings and weekends.
The scope included substantial renovation on four floors, paint and carpet upgrades on others, and a carefully planned server room upgrade. Executive assistant stations on all seven floors each needed their own weekend plan: power, data and furniture disconnected Friday at 4pm, carpet removed and floors skim-coated, new carpet and furniture Saturday, and power and data reconnected Sunday morning. That approach, along with wayfinding and indoor air quality protocols, delivered a successful turnover.